[[AFE]] - Authority for [[CAPEX]] expenditures. | [[AFE]] - Authority for [[CAPEX]] expenditures. | ||
− | [[PO]] | + | ===AFE life cycle=== |
+ | #[[AFE]] is created for [[CAPEX]] projects by the [[AFE]] Owner. | ||
+ | #[[AFE]] is approved in accordance with the [[Authority Levels]]. | ||
+ | #Money spent based on [[PO]]s attached to [[AFE]]. | ||
+ | #Project finished, [[AFE]] closed | ||
+ | #[[AFE]] actual cost is compared with planned cost | ||
===AFE Attributes=== | ===AFE Attributes=== |
Revision as of 12:18, 30 January 2017
AFE
AFE - Authority for CAPEX expenditures.
AFE life cycle
- AFE is created for CAPEX projects by the AFE Owner.
- AFE is approved in accordance with the Authority Levels.
- Money spent based on POs attached to AFE.
- Project finished, AFE closed
- AFE actual cost is compared with planned cost
AFE Attributes
- Number
- Code
- CAPEX code
- Description
- Total Cost free of VAT
- Total Cost incl. VAT
- Project Start Date
- Project Finish Date
- Attached files
AFE Status
- Status: Open/Closed
- Approval Status
- Budgeted: yes/no
AFE Authorization
Sum | Budgeted | Unbudgeted |
0-100 | Authority Levels | Authority Levels |
100-200 | Authority Levels | Authority Levels |
etc | Authority Levels | Authority Levels |